Corralling a ‘Mustang’: Taylor wrangles with fourth proposed data center

Author Avatar
Taylor's newest proposed data center would be built on U.S. 79 at the eastern edge of town.
Taylor's newest proposed data center would be built on U.S. 79 at the eastern edge of town.
Credit: Richard Stone
Getting your Trinity Audio player ready...

Residents of East Williamson County logged on to social media Tuesday afternoon to learn that a fourth data center campus is on their horizon.

The City of Taylor announced on its Facebook page and website that two companies had proposed a joint venture to build a data center campus on a 665-acre site just east of the city limits. The proposal – dubbed Project Mustang – would include a 477-megawatt, gas-powered electricity generator and at least two separate data centers.

Annexing authority

In the post, the city said that it has been negotiating a voluntary annexation of the property with the partners –- South Dakota-based Big Watt Digital LLC and PowerHouse Data Centers of Virginia.

Daniel Seguin
Daniel Seguin

“We have no ability to prevent or regulate development outside of our city limits,” said city spokesperson Daniel Seguin. “Under state law, the developers have a right to build Project Mustang in the unincorporated county, which has no zoning powers and minimal development regulations.”

Project Mustang would be built on a 665-acre data center campus abutting Taylor’s eastern city limits.
Project Mustang would be built on a 665-acre data center campus abutting Taylor’s eastern city limits.
Credit: City of Taylor

Seguin said that the city has negotiated a proposed agreement with the developers to annex the area. That would give the city authority to impose regulations addressing environmental and quality of life concerns.

No incentives

“We are not providing any incentives whatsoever and will not provide any incentives to data centers moving forward,” Seguin said. “However, if we do not annex them, they can build anyway with no regulations at all.”

Seguin said that Project Mustang tentatively agreed to exceed county and state requirements concerning such issues as water use, noise, air quality, light pollution, setbacks, buffers and stormwater drainage. Annexation also would allow the city to collect taxes and fees generated by the project.

Seguin said that the company has agreed to provide millions of dollars in grants for civic improvements and community benefits, including grants to support local scholarships and the Taylor Independent School District.

The site is near the controversial Blueprint Data Centers project and eight miles from Samsung’s massive computer chip manufacturing facility.

Moratorium demands

Opponents are skeptical of city reassurances.

Carrie D’Anna
Carrie D’Anna

Carrie D’Anna is an organizer for Halt Taylor Data Centers, which formed last year to oppose the Blueprint project on 85 acres next to a historically marginalized neighborhood on Taylor’s Southside.

“Everything happens behind closed doors then we’re told to just trust” the city, D’Anna said.

She said that organizers have known the broad outlines of the project for more than a year, but the first public statement about the project didn’t come until Tuesday.

“Everything that the public finds out is very calculated and slippery,” D’Anna said. “Even when there is information, it’s like, what are you not saying?”

Feeding these doubts was the city’s recent response to a petition seeking to impose a moratorium on future data centers. Although the city verified that residents collected the 1,400 signatures needed, Mayor Pro Tem Kelly Cmerek announced at a July 9 council meeting that the “city council has determined that under state law this measure may not be adopted through the initiative process or placed on the ballot.”

In response, Halt Taylor Data Centers members filed a writ of mandamus asking Austin’s Third Court of Appeals to order the city to let Taylor residents vote on the proposed moratorium.

D’Anna said that she wants even stricter regulations on the project and is concerned that proposed revisions to the city’s comprehensive plan and land development codes are even less stringent than those proposed for Project Mustang.

Seguin pointed out that this project has not yet been approved. “It is a proposed project that still has to go before planning and zoning as well as the city council.”

He reiterated that, absent annexation, the project could move forward without city approval or regulation. “We are working with the developer to annex the property and apply regulations to protect our neighborhoods and future developments,” he said.

Project Mustang is scheduled to go before Taylor’s planning and zoning commission on Aug. 18 and to the city council on Sept. 10 and Sept. 24.

If approved, the project would mark the Taylor area’s fourth data center campus and the 12th in Williamson County.

The city’s Mustang announcement came the day after Texas Gov. Greg Abbott put state data center projects on hold until the Public Utility Commission of Texas and the Electric Reliability Council of Texas audit all of them seeking to connect to the state’s power grid. The audits will gather information on water and power use, as well as any tax breaks obtained.

“We do not yet know how (Abbott’s order) will affect the three proposed data centers who have announced intent to build in Taylor,” Seguin said.

“Project Mustang will generate its own power and will not need the same approvals,” Seguin said. A second Taylor project is “too small” to be covered by the review process. Finally, the third project is part of “Batch Zero,” the initial group of large electricity users seeking to connect to Texas’ main electricity grid in response to the data center boom.

Williamson County’s existing and proposed data centers:

  • Sabey Data Center in Round Rock has one operational data center, one under construction and a third in the planning stage. It is expected to host the University of Texas at Austin’s Horizon supercomputer for advanced scientific research.
  • Switch campus has two operational data centers in Round Rock as part of the Dell system.
  • Skybox Old Settlers, recently approved by the Round Rock City Council, is currently the county’s only data center campus proceeding without any municipal tax incentives.
  • Thin-nology Facility operates three small data centers.
  • Hutto’s Skybox campus operates two data centers, with two more planned over the next decade. The Colovore data center in Hutto is also operational.
  • Blueprint in Georgetown is under construction.
  • Blueprint’s Taylor data center is listed as “under construction” though construction has yet to begin.
  • The city of Jarrell is negotiating an incentive agreement with Mesones Data Center, which includes an on-site natural gas generator.
  • Project Comal’s six data centers by KDC Real Estate have been permitted adjacent to the Samsung factory.
  • Iron Mountain has proposed seven data centers on about 500 acres southwest of Samsung.
  • Big Watt Digital and PowerHouse Data Centers’ “Project Mustang” in Taylor.

Richard Stone is a Central Texas native reporter and editor with 35 years of award-winning experience covering local issues that matter. More at Wilcoblues.com.