Public Works released this record in response to PIR C170285. It centers on a January 2023 Section 106 effects assessment by AmaTerra Environmental, which is required because the bridge work needs a U.S. Army Corps of Engineers permit. AmaTerra concludes that both rehabilitating the bridge and replacing it would have an adverse effect on the bridge and on the Zilker Park Historic District. The rehabilitation option would keep only the arch ribs and widen the bridge from 59 to 109 feet. Planned bike lane work would also harm a 1934 stone culvert near the park entrance.
An attached URS memo from September 2022 recommends replacement. It estimates $10.2 million to $15.5 million for a replacement bridge, against $14.5 million to $22 million for rehabilitation, which it says would leave less than half of the original structure. The packet also includes the May 2022 letter opening consultation with the Texas Historical Commission, notes from a November 2022 meeting at which the Corps agreed to serve as lead federal agency, and related emails.