On May 15, 2023, TxDOT’s Heather Ashley-Nguyen emailed city staff, the Trail Conservancy and two private parties a summary of a meeting called on short notice. The meeting covered building Lady Bird Lake boardwalks as replacement parkland for Waller Beach, which the I-35 Capital Express Central project would take. Because Waller Beach was improved with federal Land and Water Conservation Fund money, the National Park Service must approve any conversion under Section 6(f). The replacement land has to appraise at the converted land’s fair market value, which TxDOT put at $32 million. TxDOT’s slides offer three replacement sites:
- a 0.96-acre parkland dedication from a private developer, or instead 0.6 acres over the water with bank restoration
- 0.55 acres at the Seaholm waterfront
The slides also show an earlier 11-acre option appraised at $3.6 million. Under the plan, TxDOT would pay to design and build the boardwalks. It would also buy one or both water parcels if the developer’s land fell short of $32 million. The next steps were PARD sign-off, a Texas Parks and Wildlife meeting on May 25, appraisals by July 7, and a draft conversion request to NPS. If the conversion wasn’t settled before the August 2023 Record of Decision, TxDOT would commit to finding replacement land within one year. A January 31, 2023 TxDOT email included in the packet adds that the replacement land doesn’t have to be bought: city-owned, donated or swapped land can count.