In response to PIR C301343, the City of Austin released the annual project plans that the City and the Waller Creek Conservancy (renamed Waterloo Greenway Conservancy in 2019) presented to the Waller Creek Local Government Corporation. The plans come from board meetings between 2014 and 2025. The corporation was created to oversee the parks and creek restoration along Waller Creek, from 15th Street to Lady Bird Lake. The plans show the project’s estimated cost more than doubling in four years:
- $96.2 million in a 2014 draft
- $175.5 million in the FY2016 long-range plan
- $223.6 million in 2016
- $245.6 million in 2018, plus $109.3 million for operations and maintenance, for a total of $354.9 million
In 2019 the board approved a $236,040 study to update the global cost estimate and set a phasing plan. The city found no annual plans for 2020 through 2023. The FY2025 and FY2026 plans report that Waterloo Park (Phase 1) opened in 2021 and has had more than 870,000 visitors. They also report that the $86.4 million Confluence project between 4th Street and Lady Bird Lake is under construction and slated to open in 2026. The City pays 72% of the Confluence’s cost, mostly from Watershed Protection funds; the Conservancy pays 15% and the U.S. Army Corps of Engineers 13%. Design is still under way for Palm Park and the 4th–12th Street section.