This story was updated on August 1 to reflect that ATP and Greg Canally were not contacted for this report.
The three main ways that Austin plans to fund its $7.1 billion Project Connect light-rail system are all under sustained legal or political attack. Taken together, this poses existential threats to a scaled back iteration of a project that Austin voters backed when they approved a 2020 property tax increase for rail.
The Austin Transit Partnership (ATP) — a public corporation that the City of Austin and CapMetro created to oversee the rail project — has banked on two main funding streams to bankroll the project: federal grants and loans, as well as the voter-approved tax hike. To access more money sooner, ATP also plans to issue bonds and then repay that debt with future tax revenues. Significantly, all three Project Connect funding mechanisms face challenges.
Trumping Project Connect
Pinning its hopes on federal grants paying as much as 65 percent Project Connect’s $7.1 billion costs (50 percent from federal grants and 15 percent from federal loans), Austin has gone to great lengths to tee up federal funds. In May 2024 the Austin City Council fast-tracked its approval of sweeping new land-use rules known as “Home Options for Mobility and Equity” (HOME). The council expedited the new rules to promote greater urban densities that, in turn, would strengthen Project Connect’s application for Federal Transit Administration funds (dense areas facilitate mass transit).


Today, federal funding for Project Connect looks like a much tougher sell than when Democrat Pete Buttigieg was U.S. Transportation Secretary in 2024. Upon taking office earlier this year, Trump Transportation Secretary Sean Duffy issued a memo laying out how his Department of Transportation (DOT) would prioritize mass-transit projects with benefits that “outweigh the cost.”
Duffy, a former reality TV star, noted that DOT’s equation will not involve any liberal considerations of “the social cost of carbon.” DOT now favors projects with “strong co-funding requirements” that obviate the need for “future DOT support.” It will “give preference to communities with marriage and birth rates higher than the national average.” And DOT now mandates local “cooperation with Federal immigration enforcement.” It’s very challenging to construe Duffy’s memo as a win for Austin’s Project Connect.
Austin Free Press formally asked the city of Austin and the Austin Transit Project in March to disclose any documents discussing Project Connect’s: Federal funding prospects; Ridership projections; Rail-route population; and Expected impacts of HOME land-use rules on those densities. The Texas Attorney General, which oversees the Texas Public Information Act, ruled in June that the city and ATP can withhold that information under a legal exception governing ATP’s ongoing interests in its pending competitive grant application to the Federal Transit Administration.
Tax and bond challenges

Cost overruns prompted ATP to dramatically scale back Project Connect in March 2023 from the 27-mile rail system that Austin voters had approved to just 10 miles — without a price reduction. That May, Attorney General Paxton issued a nonbinding advisory opinion that questioned Project Connect’s financing.
Paxton’s opinion found that using such property-tax revenue to repay the rail bonds would violate the Texas Tax Code. It added that the Texas Constitution requires the city to appropriate property taxes for the rail project every year, rather than just once at the outset, as


ATP and the city would prefer. University of Texas finance expert John Griffin told Austin Free Press that mandating annual appropriations would increase bond repayment risks — and interest rates, increasing the ultimate price that Austin taxpayers pay for the rail project.
Meanwhile, a group of local taxpayers sued ATP in November 2023. In addition to pressing Paxton’s claims, they alleged that the city engaged in a “bait and switch” when it slashed back the scale of the voter-approved rail project. That lawsuit directs the court to block the city from collecting any more Project Connect taxes (which plaintiffs dubbed “the biggest Austin property tax increase — almost 21% — in Austin’s history”). That suit also seeks to return unspent taxes to taxpayers.
To dispel any legal doubts surrounding Project Connect bonds, ATP filed a February 2024 lawsuit that asked the courts to recognize its bond-issuing authority. The courts consolidated that bond-validation case with the one filed by Austin taxpayers. Intervening in that consolidated case, Paxton argued that ATP lacked jurisdiction to file its bond-validation suit. After an Austin state appeals court ruled for ATP last October, Paxton appealed that pending case to the Texas Supreme Court, which requested a full briefing on the case. The high court could issue a decision this fall.
Austin Free Press previously reported on “indicative ratings” that Moody’s Investors Service issued in 2024 for any bonds that ATP might issue in the future. The ratings company found that those bonds likely would have low risks and low interest rates. But Moody’s based those ratings on two false assumptions. They were that: “All current lawsuits against ATP have been dismissed;” and that ATP obtained the “validation of the Attorney General of Texas to issue the debt.”

Despite significant travails, Project Connect scored a recent victory in the Texas Legislature. Two similar GOP bills to defund the project floundered this year. Failed House Bill 3827 by Rep. Ellen Troxclair (R-Lakeway) and Senate Bill 2519 by Sen. Paul Bettencourt (R-Houston) sought to assist taxpayers challenging transit projects. The bills would have empowered plaintiffs to block tax collections “if the taxing unit has materially deviated from the purpose stated in the ballot.”
Asked in an interview to summarize her main Project Connect complaints, Rep. Troxclair said “that it is a bait and switch, we are getting a fraction of what we were promised, that the financing of this project is outside the bounds of state law, and … there is nothing (in the law) that allows a 20 or 21% permanent property tax increase into perpetuity.” She called the project “a house of cards that is going to collapse.”
Meanwhile, local critics say technology is leaving Austin’s light rail plans in the dust.

Retired Austin computer scientist Larry Akers wrote in the Austin Free Press that a fleet of 1,000 on-demand electric vans could move more passengers than Project Connect anywhere in the city – door to door – for a fraction of the cost: approximately $140 million. Contacted for this story, Akers pointed to a 2018 Bloomberg article that found that U.S. light rail cost more than $100 million per mile back then. Today, Project Connect’s forecasted costs exceed $700 million a mile.

In the face of legal and funding challenges, ATP and the city are steaming full speed ahead with Project Connect. Having hired the engineering firm AECOM to manage the project, ATP invited contractors in June to prequalify to bid on $3 billion in project design and construction contracts. ATP plans to award those contracts early next year — if the project isn’t derailed in court.
“We’ve spent a considerable amount of time and resources over the past two legislative sessions defending this voter-approved investment in light rail,” Austin Mayor Kirk Watson said in June after the anti-rail bills failed. “I do, really, think we can — and should — get this transformative mobility project done for the people of Austin.”
Andrew Wheat is the managing editor of the Austin Free Press.