Published by KUT News November 19, 2026 at 4:33 PM CST
After years of behind-the-scenes maneuvering over who would control $25 million for a new boardwalk along Lady Bird Lake, the Austin City Council approved the project Thursday under an ultimatum from the Texas Department of Transportation: Accept the deal or lose the money.
The vote came despite calls for a delay from members of the public who questioned how the project was conceived and why it took priority over other park improvements. The owner of a longtime boat tour business also warned the boardwalk could threaten his livelihood.
Council members approved two measures that would accept the TxDOT funding and put the Austin Public Facilities Corporation, an entity created by the city in 2023, in charge of designing and building the boardwalk with oversight from Austin Parks and Recreation.
Both items passed as part of the council’s consent agenda without any debate among council members; José Velásquez voted against both measures, and Marc Duchen abstained.
The arrangement marks the latest turn in a yearslong dispute over who would control the project. TxDOT and the Trail Conservancy initially explored ways to route the money directly to the nonprofit conservancy without a City Council vote, but the state agency’s lawyers blocked that approach. Parks officials objected to being sidelined and privately questioned the need for a boardwalk.
The Riverside Shores Boardwalk, as it’s been dubbed, would stretch about 760 feet along the south shore of Lady Bird Lake in front of the Hyatt Regency Austin and a luxury residential tower under construction called One Lady Bird Lake.
The 18-story tower is scheduled to be completed in 2028. The developer, New York City-based Related Companies, started selling condos in the building last month.

TxDOT
That section of the Ann and Roy Butler Hike and Bike Trail has long been identified as a tight section where the narrow path and pooling rainwater can make it hard for pedestrians and cyclists to share the path.
Under the project, the city plans to widen the existing trail and construct the boardwalk to provide an additional route over the water.
TxDOT promised the money in 2023 as part of a package of measures intended to soften the blow of its multibillion-dollar expansion of I-35 through Central Austin.
The boardwalk goes beyond the compensation required under federal law for public parkland affected by the highway expansion. The city separately accepted nearly $17.6 million from TxDOT earlier this year for those impacts.
But the promised boardwalk has yet to move beyond the planning stages amid disagreements over who would oversee construction and whether the money should be spent on this section of the trail at all.
A long dispute over control
The Trail Conservancy, which helps maintain and improve the Butler Trail under an agreement with the city, had worked with the developer of One Lady Bird Lake on an early boardwalk concept before the proposal became part of TxDOT’s plans in 2023.

Credit: The Trail Conservancy / Related Companies
Emails obtained under the Texas Public Information Act showed that TxDOT’s Austin District and Trail Conservancy officials spent months considering how the state could contract directly with the nonprofit.
But TxDOT’s own contract lawyers rejected that approach, saying the agency lacked the authority simply to select a nonprofit to do the work. Another plan emerged to use the Austin Public Facilities Corporation as a middleman to transfer the money to the Trail Conservancy without requiring a council vote.
That plan also fell apart. Now, the Austin Public Facilities Corporation will manage the project with oversight from Austin Parks and Recreation.
Records obtained by KUT News showed that senior parks officials were frustrated at being left out of early negotiations and believed the Trail Conservancy had overstated its authority over the trail to TxDOT.
Some parks officials even questioned whether a boardwalk was necessary.
Those officials tried unsuccessfully to convince TxDOT to redirect the money toward improvements they considered higher priorities, including projects at parks more directly affected by the I-35 expansion.
In February, TxDOT warned in a letter to Mayor Kirk Watson that if Austin refused to accept the boardwalk funding agreement, the agency would remove the project from its environmental commitments for the highway expansion.
Critics call for a delay
Several speakers at Thursday’s meeting urged council members to postpone their vote until more questions about the project could be answered.

Credit: Lorianne Willett / KUT News
Paul Saldaña, a founder of Hispanic Advocates Business Leaders of Austin, argued that the funding would be better spent addressing longstanding needs at parks in East Austin, where residents are dealing with the direct effects of the highway expansion.
“Decades of segregation and under-investment have left these areas with fewer amenities, while rapid development now drives displacement,” Saldaña told the council during a part of the meeting when the public can address items up for a vote.
Holly Reed, a former member of the city’s Parks and Recreation Board, also urged a delay, questioning why the boardwalk had been selected and whether the public had received enough information about the project.
Another concern came from Shannon Shaddock, owner of Capital Cruises, which has operated boat tours and rentals on Lady Bird Lake since 1991.
“While we support improving the south shore, the current plans for the boardwalk project seem to threaten to put us out of business,” Shaddock told council members.
He urged the city to involve existing waterfront businesses in the design process and ensure they can continue operating.

Credit: Michael Minasi / KUT News
Mayor Pro Tem Chito Vela was the only council member to address the boardwalk directly before the vote. He urged city staff to preserve access for boat tours, even if that means finding another location for boats to launch.
Austin’s agreement with TxDOT leaves the city on the hook for any costs exceeding the $25 million provided by TxDOT. If any of the money doesn’t get spent, it goes back to the state.
City officials say the project will be designed to fit within the available funding and that no additional money will be necessary.
Austin Transportation and Public Works — which oversaw construction of the trail’s new $25 million wishbone bridge and pedestrian tunnel — will maintain the boardwalk’s infrastructure after construction. The Trail Conservancy will handle operations, general maintenance and programming.
As for when construction starts, Austin Parks and Recreation spokesperson Dan Manco said the department is still early in the process but expects to have a better understanding of timelines within the next few months.